Improving Customer Deliveries

 

By

 

Michael J. Cote, of Supply Management Solutions

 

 

I recently meet with a Director of Operations from a large aerospace firm that was considering implementing lean manufacturing. He was still struggling with traditional MRP manufacturing practices and was concerned because customer deliveries were always late, the team members were working long hours of overtime near the end of the quarter, purchasing was paying premium prices to get needed parts and managers were jumping through hoops in order to make quarterly revenue targets. It was a discouraging and stressful situation for everyone.

 

I recalled comparable circumstances while I was Director of Materials at an electronics-manufacturing firm. Other companies face similar challenges and may be able to benefit from my experiences to improve customer satisfaction and reduce sleepless nights. 

 

Background:

We had recently acquired a small company producing a variety of power supplies. The production line (machines, workers and technology) was physically moved into the same facility but continued to "march to the tune of a different drummer".  We wouldn't even consider integrating their production processes into our system until their ability to meet customer delivery requirements improved. There was virtually no predictability and no way to tell when a product would ship. Product delivery was late 60% of the time and too early the remainder, but rarely on time! Moreover, the production line was a typical job shop operation requiring work orders and kits and had not yet been "leaned out".

 

The Problem:

A fact-finding team was formed to investigate and some interesting themes emerged immediately. The first clue was significant amounts of  "works in progress" inventory waiting for part shortages.

 

After speaking directly with the production team, I had a better understanding of the scope and nature of the problems. They indicated their frustration with purchasing which never seemed to be able to get the parts they needed when they needed them. The purchasing team presented a somewhat different slant to the problem. Purchasing explained that the planners were constantly putting material requirements inside lead times. Planners said they did this in order to keep the production floor busy and claimed that if part shortages came in based on lead- times they should be able to meet customer delivery dates. They said parts got lost in receiving or put in stock rather than being immediately delivered to the floor and this caused late deliveries. The receiving department complained they had no way of knowing if parts were short on the floor.

 

This was not a people problem, but a very broken system! Everyone was doing their best under difficult circumstances.     

 

The Solution:

With representatives from each area we discussed what we had uncovered as a team. It was clear the system itself needed to be changed and we needed some quick fixes. The manufacturing people who had products partially finished everywhere were experiencing the most significant problems and waste. This meant wasted time restarting (often more than once) the same product or similar products and resulted in quality issues. The solution was simple but drastic!  No kit would be delivered to production until all the part shortages were filled.  Furthermore, we agreed that no work orders would be issued to kit materials until the system showed all parts were available so partially filled kits would not interfere with normal warehouse activities.

 

The Results:

We started the change at the beginning of a fiscal quarter to have minimal affect on quarterly revenues. The results were dramatic. On- time deliveries increased to better than 90% by the end of the quarter. Workers weren't continually re-starting products or chasing shortages so production efficiency and quality rose. We had not yet addressed the planning problem so we still used the MRP "push" system. Things only continued to improve. Team members from each department were very pleased and embraced the changes because they felt part of the process. These small steps gave us the short-term improvements we needed to allow us to take the next step in "leaning out" the supply system.

 

 

Please visit our website, www.imaginesms.com, for more tips and information.